Milestone Report Number Two

12 December 2014

Description

Scheduled Finish

Status

Completion Date

1. Appropriateness of redeveloping the current RHH site and scope (Alignment)

This area of work will confirm the appropriateness of pursuing the Redevelopment project on the current RHH site. Advice will include the risks and benefits of allowing early works to proceed on site.

It will also examine whether the proposed hospital project scope is aligned with relevant health and clinical plans, and that the services scope is reflected in the facility scope.

End July 2014

Completed

Work has commenced and will be completed by the end of August

1 August 2014

2. Scope – (Models of Care and Facilities Management Plan)

This area of work will confirm Clinical Models of Care.

It will also examine whether there are opportunities to utilise the new hospital facilities to increase efficiencies and reduce costs for health services across the southern region.

End August 2014

Work has commenced
and is on track

 
3. Construction Methodology

This area of work will examine the costs and benefits of the two identified construction methodologies, including the associated costs, risks and benefits for patient care during the period of construction.

End October 2014

Work has commenced and is on track

 
4. Capital and Operating Financial Risks

Examine the level of capital and ongoing financial risk for the State.

End October 2014

Work will commence
during August

 
5. Ongoing Governance and Project Management

Consider the appropriate governance that would be needed for the Redevelopment RHH Project to proceed.

End October 2014

Work will commence
during September

 

Taskforce Final Report to Cabinet.

End November 2014

  

Approved: John Ramsay, RHHR Rescue Taskforce Chair, 1 August 2014